Story 03

The Technology All-Rounder

The energy transition is doubtless one of the biggest challenges of our times. It often wafts through debates like a ghost – always present, yet difficult to grasp hold of. At Koehler, the energy transition is made of solid stuff: The former coal power plant at the main site in Oberkirch, Baden-Württemberg, is being converted into a more environmentally friendly biomass combined heat and power plant under the management of Central Plant Engineering division of Koehler Innovation & Technology. We dropped by for a visit.

"Josef Hofer pays close attention to the weather report these days: “It simply cannot be windy on Saturday.” That’s because Mr. Hofer is planning to install a silo roof weighing a hefty 63 metric tons. A 45-meter tall mobile crane will put the roof, with a diameter of 23 meters, on the silo, and this can only be done without a breath of wind for safety reasons.
Mr. Hofer is a mechanical engineering technician. He works in the Central Plant Engineering division of Koehler Innovation & Technology at the company’s main site in Oberkirch. Under the leadership of this division, the Koehler Group is currently converting the coal power plant, which has been supplying the adjacent paper factory with electricity and steam since 1986, into a more eco-friendly biomass combined heat and power plant. This transition is supporting the Koehler Group’s sustainability strategy, which, by 2030, aims to generate more green energy than is required for the Group’s paper production. Mr. Hofer is heading up the conversion and keeping track of all the details together with process engineer and Corporate Director Michael Trautmann. On this sunny day in March, the two managers and Hartmut Felsch, Mill Director of Koehler Paper at Oberkirch, are visiting the construction site to see how the work is progressing. It is scheduled to be completed in fall 2024. “We are well within the scheduled timeframe,” Mr. Hofer is pleased to report."

Keeping everything under control: Josef Hofer inspects the construction work. The biomass will be presorted here in the future.

We are well within the scheduled timeframe.

We are well within the scheduled timeframe.

Josef Hofer

Project Manager for the conversion

Investment in the Future

The conversion of the coal power plant will cost the Koehler Group around 70 million euros. For Hartmut Felsch, it’s a wise investment in the future: “The construction of a new power plant would cost twice as much as the conversion.” In the future, the energy required for paper production will be obtained from burning wood chips, landscaping material, and mill residue. The combustion process generates heat, which will be used for producing steam. That will then be sent to a turbine, which will drive a power generator in the plant. “We will extract some of the steam and inject it into the paper factory, where it will be used to dry paper webs,” explains Michael Trautmann. This principle is known as cogeneration.For the Koehler Group, obtaining biomass from the region is a priority in order to keep transport routes as short as possible. Unlike coal, biomass is a renewable raw material. By switching to ;renewable energy sources, the Koehler Group expects to significantly reduce CO2 emissions by more than 150,000 metric tons per year at the Oberkirch site. This will not only contribute to the company becoming carbon neutral – by 2030, it wants to generate more green energy than it needs for paper production – but will also help to reduce Germany’s carbon footprint. Importantly, the new biomass combined heat and power plant will also make the Koehler Group more resilient to crises, because it will not be dependent on energy supplies from abroad, as is often the case with gas, for example.

From left to right: Hartmut Felsch, Josef Hofer, Theo Maier, and Michael Trautmann discuss the installation of a silo roof.

Complex Project

The Central Plant Engineering division, together with colleagues at Koehler Renewable Energy, began working on the plans to convert the power plant to a sustainable raw material back in 2018. “It is a very complex project,” the division’s Corporate Director Michael Trautmann points out. The conversion requires a permit under the German Federal Immission Control Act (Bundes-Immissionsschutzgesetz), including a building application. The division liaised with the City of Oberkirch and Freiburg regional council to ensure that the necessary legal basis was in place for this. Talks were also held with architects, structural engineers, and many other trades besides, focusing on the boiler conversion, fuel supply, and all of the required infrastructure measures. The team is currently coordinating the installation work and adapting the infrastructure in the existing power plant. At the end of the project, it will also assist the commissioning process right through to the handover to the power plant operator. “All power plants operate on a similar principle, regardless of the energy source,” emphasizes Josef Hofer. Nevertheless, various conversion measures are required to adapt the coal power plant to the new fuel. For example, workers are currently building two receiving stations for unloading the material from trucks, four silos for storing the biomass, and conveyor belts for transporting the fuel onward to the boiler. As the new power plant will run around the clock, 365 days a year, stocks of fuel will be required – for example, for public holidays, when there will be no deliveries. The crucial step was taken in June with the construction of the boiler. The construction site team installed the new fuel supply system in the boiler house, which will convey the wood to the boiler. The entire combined heat and power plant is idle during the process. Nonetheless, paper production in the neighboring plant continued uninterrupted, explains Josef Hofer. “The steam for that will come from the cold reserve, which to all intents and purposes functions as a replacement power plant.”

>60

employees work in Central Plant Engineering.

The team is well within the scheduled timeframe for the construction work, which should be completed in fall 2024.

Combined Expertise

The 60 plus employees in the Central Plant Engineering division are responsible for the planning, scheduling, and execution of technical projects. Their work has changed considerably over the decades, says Corporate Director Michael Trautmann. “Originally, the division was a technical office with a handful of colleagues who produced the technical drawings and designs themselves.” With more than 100 large and small projects a year, there are plenty of other tasks too. That’s why Central Plant Engineering is now the hub where information from all project stakeholders comes together. “Our core is the planning department, which has around 40 employees,” explains Mr. Trautmann. This is divided into Mechanical Planning, Electrical Engineering Planning, and Construction Planning. “The other departments deal with procuring services and technical systems, as well as technical products and project components. We also have an Environmental Protection and Facility Licensing team, which handles all of the relevant official and legal applications and reports for executing projects.” In other words, Central Plant Engineering has experts in all relevant fields and can offer its internal customers a complete package.
Michael Trautmann expects projects like this to become a more frequent occurrence in the future because of the Koehler Group’s sustainability strategy: “We are proud to be facilitating and supporting such a positive development.”"

We are proud to be supporting such a positive development.

We are proud to be supporting such a positive development.

Michael Trautmann

Corporate Director Central Plant Engineering

Story 02

Sustainability on a Roll

Story 04

From Partners to Friends